MIRNEWS.254 16 MAY 1995 2d Spacewalk (EVA) MIR-crew: The crew of the 18th Main Expedition, Dezhurov and Strekalov, will do their 2d EVA on 17.05.1995. This EVA will begin at 0247UTC (opening of the hatch) and will end at 0820UTC (clo sing the hatch.) The cosmonauts will fold up and transfer one of the solarpanels of Kristall (Module-T) to the outersurface of the astrophysical module Kvant-1. They will use the Strela- crane as a lever. The cosmonauts have to make complicated manoeuvres with Strela: they have to reach the Kristall module first and later on swing over to the Kvant-1 with their 'cargo'. The American astronaut, Norman Thagard, will stay inside the complex and execute commands if necessary. Today he even practised the loading of date in the movementscomputer of the complex. 1st EVA (correction and completion): At the moment of the closure of the Altair/MIR window on 12.05.95 at 0937UTC I was sure that the EVA was still going on. However I believed a spokesman who stated that the hatch had been closed at 0935UTC. In fact the EVA lasted 1 hour longer until 1035UTC (1335 TsUP Time and not Moscow summerti me) so exceeding the planned EVA with 1 hour and the guaranted security period for the spacesuits with 15 minutes. The cosmonauts were very tired when they came back on board, but satisfied for the EVA was a success. Launch of Spektr: Still on schedule for 20.05.1995. Chris v.d. Berg, NL-9165/A-UK3202.