MIRNEWS.356 25 APRIL 1997 1st Spacewalk (EVA) MIR 23/NASA 4: Vo chto by to ni stalo. This is the Russian analogue for 'At any cost'. Monitoring radiotraffic during the last days I realised that those responsible for this MIR/NASA expedition decided to stick to the EVA on 29.04.97 and this made me use this expression as a sub-title for my report about that EVA. In fact I expected that the long sequence of serious technical problems and consequently the enormous strain for the crew justified the cancellation or at least a suspension of that EVA. Officially has been announced that the situation on board is almost back to normal and that the health condition of Tsibliyev and Linenger is such that they can do that EVA. The EVA is on schedule for 29.04.1997 at 0450UTC (opening of the hatch) and will last 5 hours and 30 minutes. Using spacesuits of a new design delivered to MIR by the freighter Progress-M34, Tsibliyev and Linenger will install American experiments at the outersurfaces of Kvant-2 (Module-D) and the SO (the docking compartment at the Kristall (Module-T). They also will retrieve similar experiments which had been installed there in the past. Today the 'spacewalkers' trained for that EVA. In the past the preparations for EVA's started a long time before the planned date en during the last few days crews always fully concentrated on the oncoming EVA. They always got 1 or 2 days off to enable them to start the EVA as fit as possible. This time the preparations started only a few days ago and they had to use a part of the time for maintenance and repair activities. The cosmonauts are very tired and they yearn for a day off. Another problem during this EVA is the communications infrastructure. There is no Luch available. Altair-2 is still moving to the West and not operational at the moment. In the very beginning when there were no geostationary satellites availble for MIR-TsUP (or: Salyut - Zarya) communications Russia had a fleet of trackingships all over the world. Of this fleet only 4 ships are left, 2 of which are operational, but they have to remain in St Petersburg until there are means for exploitation. It is true that TsUP has the possiblity to use Dryden and Wallops in the USA and Oberpfaffenhofen in Germany, but that is not enough to fill up all the gaps in the infrastructure. Telemetry monitoring during EVA's is essential. If all goes well Tsibliyev and Linenger can be heard while they are on their way back to the airlock of Module-D during MIR's orbit 63941 between 1000 and 1030UTC on 29.04. During a short interview with an American radiostation Linenger on 23.04.1997 told, that they had a rough time, but that they succeeded in restoring the situation almost back to normal and that they all were doing fine. About the leakages of the cooling system in Kvant-1 and the eventual influence of ethylene glycol on the health of the crew he said that the effects in the long run are still unknown. Solar orbit: In my MIRNEWS.355 I suggested that the next period in which the MIR- complex would remain permanently in the sun was to begin in a 'few' days. This was an error. The next solar-orbit period will be in the first week of June. Chris v.d. Berg, NL-9165/A-UK3202.